The Simpson County Board of Supervisors met Monday, August 3, 2015 at 9:00 am. Two people were in attendance other than the required members and administration. The minutes for July were approved. Buddy Wolverton, County Engineer gave the following report:
LSBP-64(20) – Matt Lee Road (Bridge)
P.S. E. Assembly mailed to State Aid on August 13, 2014.
Awaiting Funding
LSBP-64(21) – Dollar Road
91.28% Complete
80.00% Elapsed Time
Held final inspection. Contractor has been given a punchlist.
SAP-64(62) – Hopewell Road
Have issued Notice to Proceed. Contractor should start late August.
STP/BR-0064(22)B – COX Road
P.S.& E. Assembly mailed to State Aid on July 28, 2015.
Awaiting funding.
SAP-64(16)S – JUPITER ROAD(PART), COOOPER ROAD (PART),
S.E. SILOAM AVE, SILOAM CHURCH ROAD, AIRPORT ROAD
(PART), AND HEED NEELY ROAD.
98% Complete
65% Elapsed Time
Contractor gas completed all major items of construction. Have
Requested a final inspection.
Road Manager J.M. Hooker gave the following report:
- Road Mangers Monthly Report
- Easement/ Mark Harris/ Ditch Dirt
- MDOT Driveway Application / Britt Magee
- Board approved all recommendations.
Sheriff Lewis had no information to report at this time.
Tax Assessor Charles Baldwin gave an update on the tax roles and modifications that were needed.
No new business was discussed. Next meeting will be August 14th. Meeting was adjourned.